Project planning

When

What

2nd quarter 2015 Completion Area inside the dike
2nd quarter 2015 Completion Promenade bridge
3rd quarter 2015 Completion Extended Waal bridge
3rd quarter 2015 Completion Dike / New quay Lent
4th quarter 2015 Completion Citadel bridge
4th quarter 2015 Completion Ancillary Channel
4th quarter 2015 Completion island Veur-Lent
2nd quarter 2016

Completion total project i-Lent

projectplanning